About Geo!
The Northern
California Power Agency is the owner and operator of two geothermal
power plants and the associated steam field. The project is part of the
Geysers Known Geothermal Resource Area (KGRA) located in the scenic
Mayacamus Mountian Range 75 miles north of San Francisco. The Geysers KGRA is the largest
producer of geothermal electrical energy in the world, providing clean
(low emissions of the "green house" gas carbon dioxide and no emissions
of air toxins associated with the combustion of fossil fuels), renewable
energy for California. NCPA is proud to be part of this valuable "green"
energy source. The NCPA power plants are registered by the California
Energy Commission as a Registered Renewable Supplier I. D. Number
CEC-40021.
The two NCPA power
plants each house two 55 megwatt nameplate turbine generators and
associated equipment. Dry superheated steam is delivered to the power
plants from 65 to 70 production wells via approximately 8 miles of
pipeline. The NCPA Plant 1 was first paralleled to the grid on New
Year's Day 1983 with Plant 2 coming on line some twenty-two months later
in November of 1985. Since that time the NCPA power plants have been a
valuable and reliable generation asset for the members of NCPA,
operating with a greater than 95% availability.
Toward the end of
the 1980's reservoir engineers at the Geysers discovered that steam
pressure within the geothermal reservoir was declining at a higher than
expected rate due primarily to over porduction of the resource by the
various companies operating power plants at the Geysers. Continued high
decline rates threatened to significantly reduce the life of the Geysers
as a valuable renewable energy source. NCPA was the first operator at
the Geyers to aggressively take steps to try and reverse the pressure
decline trend.
NCPA's initial
effort to limit decline involved changing its mode of operation of the
plants from a base loaded operation to a load following mode of
operation, where electrical output of the plants was limited during off
peak hours of the day and increased during peak hours. Annual average
output from the plants was reduced from a high of 248 megwatts to 155
megwatts to obtain maximum long-term benefits from the geothermal
project. The NCPA plants were the first geothermal plants to be cycled
on a regular basis.
To fully utilize
some of the lower pressure steam found in certain sections of the NCPA
reservoir, NCPA modified its Plant 1, Unit 2 turbine to a low pressure
turbine in 1996, along with the steam field piping and computer control
systems. This allowed the lower pressure steam to be dedicated to the
low-pressure turbine whereby turbine-generator outputs were maintained
even at the lower pressure.
NCPA found that
while reservoir pressure was declining, heat within the reservoir was
not. Water injected into the reservoir via strategically selected
production wells (typically low steam producing wells and/or wells with
a communicating fracture system within the resevoir to other production
wells) was readily converted to steam, helping to lessen the effects of
the pressure decline. To this end, NCPA constructed two water retention
dams near each of the power plants that collect rainwater runoff for
injection into the resevoir. This rainwater supplemented the condensate
blowdown from each plant that was already being injected. Resevoir
testing found that the reservoir was capable of converting even more
injection water to steam than there was water available. To maximize the
benefits of augmented injection, NCPA partnered with other operators at
the Geysers and the Lake County Sanitation District to pump treated
effluent from the City of Clearlake, California some 28 miles up to the
Geysers field for injection.This Effluent Pipeline Project has helped to
further extend the life of the NCPA geothermal project by offsetting
some of the pressure decline effects of the reservoir. Five to eight
wells are utilized as injection wells to handle the augmented injection
program.
A byproduct of the
conversion of geothermal energy to electricity at the Geysers is
elemental sulfur. The sulfur is produced during the chemical abatement
of hydrogen sulfide gas, a naturally occurring noncondensible gas with a
noxious order that is produced along with the geothermal steam. In the
early years of the NCPA project, this sulfur was treated as a hazardous
waste due to trace amounts of mercury, also a natural occurring
constituent of the geothermal steam produced at the Geysers. Through
technological innovation, a method to remove mercury was developed that
now renders the sulfur nonhazardous. The sulfur is now utilized as a
feedstock in the California agricultural fertilizer industry, benefiting
the environment by eliminating the need to landfill the material. NCPA
maintains an on-site laboratory certified by the California Department
of Health Services as an Environmental Testing Laboratory. The
laboratory tests every shipment of sulfur leaving the site to ensure
that it meets all regulations connected to its classsification as a
nonhazardous byproduct.
The NCPA geothermal
project has established itself as a leader in the industry, and through
the dedicated efforts of the NCPA staff, will continue to be a leader
for many more years into the future.
t